Map of Facility

2018



Big Lift warehouse construction completed



Phase I south wharf reconstruction completed



80 acres acquired



Design for new maritime cargo warehouse and road improvements began

2019



700 Smith Blvd 11 acre pre-development begins



Ro-Ro and south wharf final reconstruction complete



New maritime cargo warehouse construction begins



Port expansion – Permit, SEQRA and approvals, initial construction

2020-2021



Shed 1 demo



Maritime terminal reconstruction



Building demolition and maritime terminal storage expansion



Smith Blvd reconstruction and improvements