Map of Facility
2018
Big Lift warehouse construction completed
Phase I south wharf reconstruction completed
80 acres acquired
Design for new maritime cargo warehouse and road improvements began
2019
700 Smith Blvd 11 acre pre-development begins
Ro-Ro and south wharf final reconstruction complete
New maritime cargo warehouse construction begins
Port expansion – Permit, SEQRA and approvals, initial construction
2020-2021
Shed 1 demo
Maritime terminal reconstruction
Building demolition and maritime terminal storage expansion
Smith Blvd reconstruction and improvements